Construction Update: Marina Twin Tower Residences Completed
Date: 6 October 2008 Current Temp: 12 C Q Island Marina Data: 71% Completed
Q Signatures Island, Monday 1529 pm- Emirates Architect & Developers has finally completed their latest project developments,the Marina Twin Towers Residences.Developer Manager,Kabin Ahmedi Omar,launches the opening ceremnony and key giveouts to residences or customers to move in to their new duplexes.Tower 1 is fully occupied and sold out while Tower 2 is nearly 89% occupied.At the base of the towers there is a gymnasium,health club,retail stores,24 hour store and a nursery.
Timeline and Construction Progress Of Marina Tower 1 & 2
27 December 2006.
13 February 2007.
31 August 2007.
1 January 2008.
13 July 2008. ( Marina Tower 1 Topped Out )
1 October 2008. ( Marina Tower 1 & 2 Completed And Fully Furbished )
Day/Night Pics Of the Marina Twin Towers.
Stay tuned for more update my friends
Comments and reviews appreciated!!
Comments
Post a Comment